A new high-voltage substation is currently being built near the recycling center in Sterrebeek. In 2027, the construction of a new underground cable connection between the high-voltage substations in Zaventem and Woluwe, via the new substation in Sterrebeek, is scheduled to begin. These works aim to increase the capacity of the electricity grid to meet the growing demand for electricity. The works are being carried out by Elia, the manager of the Belgian high-voltage grid, as part of the approved investment plan of the Flemish Region.
The environmental permit application for the cable connection will be submitted in November 2026, followed by a public inquiry. If the environmental permit is obtained, construction is expected to start in August 2027 and last until 2029-2030.
During the information market, Elia will provide more details on the purpose, timing, and potential impact of the works. Project managers will be available to answer questions.
The information market will take place on Tuesday, December 1st from 6 PM to 8 PM at Silversquare Zaventem, Ikaroslaan 1, 1930 Zaventem. Registration is possible via the QR code or the free number 0800 11 089.