The works, scheduled for the weekends of November 6-9 and November 13-16, as well as the nights of November 9-14, are expected to cause limited disruption. However, local residents may experience noise, construction traffic, and night lighting.
This initial phase focuses on maintaining the existing railway bridge. In Spring 2027, larger renovation works are planned, which will include widening the bridge to create pedestrian walkways and renewing elements such as the parapets and waterproofing. Further information on this will be provided later.
The impact of the works includes potential noise disturbance from work trains and machinery, the presence of construction traffic and personnel in the vicinity, and the use of site lighting during night works. When continuous work is carried out, train traffic will be interrupted. Travellers can consult the adjusted timetable via the journey planner on the NMBS website or their app.