Rapenbrug Renovation in Maldegem Delayed Until Late February 2027

Unexpected corrosion and weather conditions cause an extension of the works on the Afleidingskanaal van de Leie.

(vergroot foto)

Gemeente Maldegem

The renovation works on the Rapenbrug over the Afleidingskanaal van de Leie in Maldegem, which began in March 2026, are proving more complex than expected and are now projected to conclude by late February 2027.

The project, initially scheduled to end in late October 2026, faced delays due to the discovery of magnetite, a difficult-to-remove form of corrosion, after the old protective layer was removed in June 2026. This type of corrosion poses a threat to the metal's lifespan.
To compensate for lost time, the contractor continued work during the summer construction holiday. All magnetite was removed, and new steel was welded where holes or thinning had occurred, a process more extensive than initially estimated. The superstructure is now complete up to the intermediate layer. The substructure is currently being blasted in sections and coated with a base layer of protective paint, which must be done in smaller segments due to climatic conditions.
Applying the intermediate layers to the substructure and the final topcoat to the entire bridge requires specific climatic conditions, which are harder to control during the darker months. Furthermore, the storm of October 23 and 24, 2026, necessitated the removal and reinstallation of the protective sheeting for safety reasons, causing further delays.
Following the painting, various other tasks remain, including installing new wooden cladding for the roadway and footpaths, concrete repairs, asphalting the approaches, and fitting the railings. The objective of these works is to guarantee the bridge's lifespan for the coming decades.
De Vlaamse Waterweg nv and the contractor acknowledge the inconvenience caused. The municipality urges for the works to be carried out as smoothly as possible. The diversions for motorized traffic via Aardenburgkalseide (N410), Rijksweg (N251), Brieversweg, Vuilpanstraat, Vlotweg, Moerhuizebrug, Lievestraat, and Moerhuizestraat will remain in place. Local businesses remain accessible via these diversions. Cyclists can use the towpath along the Schipdonkkanaal, Aardenburgkalseide (N410), Vlotweg, Moerhuizebrug, Lievestraat, and Moerhuizestraat.
Based on information from the official source: Gemeente Maldegem (19/11/2026)