The production of bridge components for the renovation of the bridge on Zeelaan and Prins Boudewijnlaan (N9) between Maldegem and Eeklo is taking longer than previously expected. Consequently, the current completion date has been moved from March 2027 to early June 2027. The Agency for Roads and Traffic (AWV) acknowledges this is unwelcome news for residents, businesses, and road users.
It was announced in early October that the works would not be completed by the original deadline of late 2026, but in March 2027. The renovation, which preserves the existing piers, is custom work. This led to a longer study period and delays in the production and delivery of specific bridge parts that are not manufactured to standard dimensions. The manufacturing of these components requires more manual labor than initially estimated.
This delay impacts subsequent work. For instance, the concrete for the bridge deck cannot be poured before the Christmas holidays, and the construction leave period cannot be used for curing. Based on the current schedule and expected weather delays during winter, the final completion date is now pushed to early June 2027.
Roads and Traffic understands the significant impact of this new delay and the concerns raised by the municipalities of Maldegem and Eeklo. Residents and road users face longer detours, and businesses in the area experience a prolonged difficult period. The agency, along with the contractor, will continue to explore opportunities to save time during the execution, depending on technical feasibility, the contractor's schedule, and weather conditions. Early June remains the most realistic projection based on current information.
The traffic measures will remain in place following consultations between the Agency for Roads and Traffic, the municipality of Maldegem, the city of Eeklo, and the police services. The suggestion to open the Balgerhoeke bridge in both directions was not adopted as the local connection cannot handle the traffic volumes from the N9. Opening the bridge would be detrimental to safety, liveability, and traffic flow. The main detour remains via the N49/E34, with existing local diversions continuing. Businesses along Zeelaan, Prins Boudewijnlaan, and surrounding streets will remain accessible.