City of Menen: update on sewer works in 't Paradijs district

Overview of progress in Neerweg and Vagevuurstraat, with new schedules and traffic measures until after the Christmas break.

Generic image of a road with orange barriers and yellow tape, typical for roadworks in a residential area.
AI

Generic image of a road with orange barriers and yellow tape, typical for roadworks in a residential area.

The city of Menen has released an update on ongoing sewer works in the 't Paradijs district in Rekkem. Works in the Neerweg and Vagevuurstraat are underway, with specific schedules and measures in place until after the Christmas break.

Key points

  • Pumping station in Paradijsstraat 161-185 is operational
  • Works in Neerweg and Vagevuurstraat resume week of 23 November
According to the city, works in the Neerweg and Vagevuurstraat are fully underway. In phase 2B (Paradijsstraat 161-185), the pumping station has been successfully started. In phase 3A (Neerweg), all street gutters, curbs, and sub-base have been placed. Part of the base layer has already been asphalted, and the intersection has been fully cast in washed concrete. In phase 5A (Vagevuurstraat 2-60), the sewerage up to the Vaandelstraat intersection has been placed, and house connections on the even side are fully completed.
Works in phase 4A (side branch Neerweg 68 – Vagevuurstraat 79) were temporarily halted due to high groundwater levels but will resume in the week of 23 November. In the Vagevuurstraat, the placement of street gutters and curbs will also begin then. The contractor aims to complete the foundation of the roadway and sidewalks in the Neerweg and Vagevuurstraat before the Christmas break.
Traffic management measures are in place until after the Christmas break. The intersection in the Neerweg will be opened during the Christmas break, but for now, there is no through traffic possible in the Neerweg. The following streets will remain dead-end until after the Christmas break: Paradijsstraat from no. 141, Schelpenstraat from the Grote Weg intersection, Vagevuurstraat from the Vaandelstraat intersection to no. 2, and Neerweg from the Dynastielaan intersection to no. 1A. The Ten Bulcke district remains accessible via the Schelpenstraat/Grote Weg intersection.
The city warns road users that not all renovated parts of the street will be salted this winter. Washed concrete and new asphalt can be damaged by road salt. The new concrete must withstand one winter before road salt can be used. No salting is allowed on places where only the base layer has been laid. The city asks road users to be extra careful during the winter period.
After the Christmas break, the city will evaluate with the contractor whether the Vagevuurstraat x Neerweg intersection can remain permanently open. This will depend on whether the operation and execution of future phases allow for it. For questions about utility services, residents can contact the respective companies (De Watergroep, Fluvius, Telenet, Proximus). For information on the works, contact Aquafin, the contractor Cnockaert Construct, or the Public Works department of the city of Menen.
Based on information from the official source: Stad Menen — Nieuws (26/11/2026)