The works are necessary for the preservation and future of the village church. Maintenance and repairs are needed for the masonry and pointing, treatment against rising damp, roof and lead work, minor electrical work, carpentry in the attic, repairs to exterior joinery, painting, and repairs to the pavement around the church.
Once the exterior restoration is complete, the landscaping will follow, transforming the garden around the church into a green oasis in the village center. During working hours, aerial work platforms and vehicles will be on site, using access mats around the church and occupying parking spaces in Gasthuisstraat. These spaces will be available in the evenings and on weekends.
Occasionally, delivery trucks may cause brief traffic disruptions when temporarily on the roadway.
The work will take place from November 16, 2026, to Tuesday, March 23, 2027. Weather conditions such as severe frost or heavy rain may affect this schedule.