De Vlaamse Waterweg nv will mount the new arch bridge over the Netekanaal during the weekend of November 20, 2026. To ensure the safe execution of the mounting, the following measures will be taken.
The Nijlensesteenweg N116 will be closed at the bridge for all traffic from Saturday, November 21, 2026, at 6 AM to Sunday, November 22, 2026, at 6 AM. Motorized traffic will follow local detour routes.
The towpaths along both banks in the work area will be interrupted from Friday, November 20, 2026, at 6 AM to Monday, November 23, 2026, at 6 PM. Cyclists and pedestrians will follow a detour via the towpath on the left bank of the Kleine Nete. They can cross the Netekanaal via the bridge of Emblem and at the lock of Viersel.
Finally, shipping traffic in the vicinity of the construction zone will be completely suspended from Saturday, November 21, 2026, at 6 AM to Sunday, November 22, 2026, at 11:59 PM. If the works are completed earlier, the detours will also be lifted ahead of schedule.